711 N. High St.

Location: Columbus Ohio
Client: Dugan & Meyers
Duration: 1 Year
Scope: 24,000 SF of air barrier, 3,300 SF of traffic coating, 2,700 SF of waterproofing, 20,000 LF of sealant work.
Owner: The Wood Company

View All Projects

Description of Work

Air barrier, Caulking, Coating, Sealer

Accomplishments

Accessing the building with limited space and scheduling delivers to location. Two sides were land locked, one side was a small alley and the forth was High St. This location isn’t very far from OSU campus or the Columbus Convention center so it’s very busy. Learning how to utilize different means of access in order to complete your tasks.

Related Projects

Cincinnati Union Terminal Interior Cladding Restoration

View Project

Food Processing Facility Slab Replacement

View Project

The Ohio State University – Building Exterior Repairs

View Project

Let’s Talk About Your Project

Talk to one of our pre construction staff today about your project and needs.
Each engagement is unique, and we love finding distinctive solutions to your problems.

Get in Touch